Solar Project at Ballyfabs Belur | HCK Solar Case Study

Ballyfabs International Belur Unit

Rooftop Solar Power Plant at Ballyfabs International – Belur Unit

Client: Ballyfabs International – Belur Unit

Location: Belur, West Bengal

Industry: Textile Manufacturing

Capacity: To Be Confirmed (based on client data)

Installation Type: Rooftop Shed Mount

Model: CAPEX (Client-owned)

Project Partner: HCK Solar Energy Limited

Project Overview

Ballyfabs International's Belur unit sought a renewable energy solution to lower operational costs and enhance sustainability. With substantial power needs for manufacturing, the company partnered with HCK Solar Energy Limited to implement a customized rooftop solar plant.

Objectives

  • Reduce energy costs associated with industrial operations
  • Minimize reliance on conventional electricity grids
  • Utilize available shed rooftops for solar deployment
  • Achieve long-term savings through CAPEX investment

Our Solution

HCK Solar conducted a detailed feasibility study and structural inspection to design a tailored solar PV system. The setup is engineered to ensure safety, high performance, and minimal disruption during installation.

Technical Highlights (Indicative):

  • Tier-1 Monocrystalline Solar Modules
  • High-efficiency string inverters
  • Penetrative or non-penetrative mounting based on shed structure
  • IoT-enabled performance monitoring
  • Safety features: earthing, surge protection, fire safety compliance

Project Execution (Estimated)

  • Site Survey & Feasibility: 1 Week
  • Design & Structural Assessment: 1 Week
  • Procurement & Logistics: 2 Weeks
  • Installation & Commissioning: 3 Weeks
  • Net Metering Coordination: 1 Week
  • Total Duration: 8 Weeks

Expected Results & Impact

  • Average Monthly Generation: To Be Finalized
  • Cost Savings: Substantial reduction in electricity bills
  • Annual CO₂ Reduction: Significant carbon offset expected
  • Payback Period: Estimated 3–4 Years

Why HCK Solar Was Selected

  • Industrial rooftop solar expertise
  • Optimized structural design and engineering
  • Proven CAPEX model implementation
  • Efficient and safe execution practices

Impact

The solar project enables Ballyfabs International’s Belur unit to move toward cleaner energy adoption, cost efficiency, and reduced carbon emissions. The installation will contribute to long-term operational stability.

Client Testimonial

What impressed us most about HCK Solar was their transparency and engineering expertise. They helped us choose the right equipment from multiple brands and ensured optimal system performance. Their vendor-neutral approach gave us complete confidence that we were getting the best value and technology for our investment.

Rajesh Bodhale, Executive Director Ballyfabs International